Mayor Brandon Johnson Breaks Ground on $917 Million New Concourse E at O’Hare | aviationbizz.com
Mayor Brandon Johnson today joined the Chicago Department of Aviation (CDA), United Airlines, American Airlines and project partners to break ground on The New Concourse E, marking the next major milestone in the historic ORDNext modernization program at O’Hare International Airport.
The $917 million New Concourse E will add 24 gates at O’Hare through two phases of construction. The $640 million first phase, targeted for completion in 2030, will construct 14 new gates and approximately 315,000 square feet of new passenger space. A $277 million second phase will extend the concourse with 10 additional gates following completion of the O’Hare Global Terminal in late 2033, bringing The New Concourse E to its full 24-gate configuration in 2034.
“We are making tremendous progress on the ORDNext modernization program, and this groundbreaking demonstrates our commitment to building on that momentum,” said Mayor Brandon Johnson. “Advancing this major investment strengthens O’Hare’s future as a global hub, creates good-paying jobs and expands opportunities for generational wealth in communities across Chicago. At the same time, we are building the modern facilities necessary to keep millions of passengers moving and ensure O’Hare remains the world’s busiest airfield for generations to come.”
In August, CDA announced an updated construction sequence that allows the first phase of The New Concourse E to advance concurrently with The New Concourse D. The approach will create the additional gate capacity needed to support an accelerated construction schedule for the O’Hare Global Terminal, which is scheduled to begin construction in 2029 and be delivered in a single, coordinated phase by late 2033.
The first phase of The New Concourse E will include 14 domestic-capable gates, holdrooms with ample seating, nearly 21,000 square feet of concession space and a new public art program. The two-level concourse will stretch more than 1,000 feet and will be primarily accessed through an underground passenger tunnel connecting it with The New Concourse D, scheduled for completion in late 2028.
“Passenger demand at O’Hare continues to grow, and our job is to make sure the airport is ready not only for the travelers we serve today, but for the millions more we expect in the decades ahead,” said CDA Commissioner Michael McMurray. “Beginning construction on The New Concourse E now allows us to add gates sooner, create the capacity necessary to advance the O’Hare Global Terminal and deliver the overall ORDNext program more efficiently. It is a sequencing strategy that makes sense operationally and financially while keeping O’Hare positioned to compete as one of the world’s leading aviation hubs.”
“Concourse E is about building on O’Hare’s success and preparing for what’s ahead, with modern facilities that will help the airport operate efficiently, accommodate future growth and deliver an even better experience for our customers,” said Andrew Nocella, United’s Executive Vice President and Chief Commercial Officer. “As Chicago’s hometown airline, we know a stronger O’Hare means a stronger Chicago, and that benefits everyone who works here, travels through here and depends on this airport to connect with the world.”
“This milestone in ORDNext is an important step toward the next generation of O’Hare and the O’Hare Global Terminal, which will transform the experience for our customers and create new possibilities for where American can take them,” said American Airlines Chief Commercial Officer Nat Pieper. “American’s century-long commitment to Chicago has helped shape O’Hare into one of the world’s leading aviation hubs and this project builds on the investments we’re making across Chicagoland to make it even stronger for the long term. We’re grateful to the City of Chicago and CDA for their shared vision and partnership in moving this historic transformation forward.”
New renderings released today showcase a design by Skidmore, Owings & Merrill (SOM), in collaboration with Ross Barney Architects, Juan Gabriel Moreno Architects (JGMA) and Arup, that extends the architectural language of The New Concourse D while creating a distinct passenger experience inspired by Chicago and the natural landscape of the Midwest. The New Concourse E brings together the same design and construction teams responsible for The New Concourse D, with construction led by the AECOM Hunt Clayco Bowa joint venture. Connect Chicago Alliance (CCA) serves as CDA’s program management team for ORDNext, overseeing planning, design and construction coordination across the program.
“Building on our team’s skilled work on The New Concourse D, we’re proud to now extend our commitment and aviation sector expertise to The New Concourse E, ensuring it is delivered on time, on budget, and stands as a benchmark for innovation in airport infrastructure,” said Eric Howe, Senior Vice President, AECOM Hunt. “Our work will help usher in this project’s vision for a transformative passenger experience and serve as a model for what’s possible in the delivery of large-scale infrastructure projects. Together, we will carry forward O’Hare’s legacy as one of the world’s great aviation gateways.”
“New Concourse E represents the next chapter in how Chicagoans and visitors experience O’Hare,” said SOM Partner Scott Duncan. “Building on our vision for Concourse D, we’re creating light-filled, open spaces inspired by Midwestern landscapes to make travel easier, more comfortable, and more enjoyable.”
The design also anticipates the concourse’s future expansion. At its southern end, a curtain wall system will be designed to be relocated and reused when the second phase adds 10 more gates, allowing the building to expand with minimal disruption to airport operations. The project includes installation of the utility loop around Concourse E, anticipating the full expanse of, and forecast capacity of the full Concourse E.
“Passengers will experience these projects as one airport, and we have to manage them that way,” said Dave Nisula, Program Manager for Connect Chicago Alliance, the CDA’s Program Management Office. “Decisions about Concourse E have to account for the tunnel connections, the work underway on Concourse D and the future Global Terminal. Our job is to make sure those pieces come together efficiently, from design through opening day.”
Today’s groundbreaking follows a series of major construction milestones across ORDNext. In June, the City finalized a Guaranteed Maximum Price of $1.455 billion for The New Concourse D, $21 million below its initially approved budget. Vertical construction is now underway on the 19-gate concourse, which remains scheduled for completion in late 2028.
Together, The New Concourse D, The New Concourse E and the O’Hare Global Terminal represent the centerpiece of ORDNext, the largest terminal expansion in O’Hare’s history. When completed, the program will increase O’Hare’s gate capacity by approximately 14%, creating room for new routes and destinations, strengthening hub connectivity and delivering a more modern passenger experience at one of the world’s most important aviation gateways.